Description

The Town of Marathon has received funding from the Northern Ontario Heritage Fund Corporation (NOHFC) and FedNor to complete a major upgrade to the Pebble Beach viewing area. 

We know residents and tourist alike enjoy taking in the views of the lake, but during construction this area will be off limits. Alternate viewing areas that will be safe to access during this time will be posted and shared throughout the project.

Location

38 Howe Street, Marathon, ON

Schedule

Construction to start May 2023.

*The area is closed to the public starting May 8, 2023*

Budget

$1,351,762.80 

$450,000 NOHFC Funding

$450,000 FedNor Funding

$451,762.80 Municipal Budget

Documents

Pebble Beach post tender addendum